Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

B.C. Hydro’s Site C set back by COVID-19, foundation changes

Peace River diversion still on track for this fall

B.C. Hydro’s plan to have the third dam on the Peace River complete and in service by 2024 has been set back by work scaling down due to COVID-19 restrictions on construction projects, and additional foundation strengthening for the powerhouse and spillway.

In a progress report filed with the B.C. Utilities Commission July 31, B.C. Hydro CEO Chris O’Riley says the Site C project is still on track to divert the Peace River through a pair of tunnels and begin in-river work. But that too has been complicated by geological conditions. The financial impact of the coronavirus delays and additional work will be better known in the fall, O’Riley said.

“Pandemic-related delays will present further cost pressure on the budget,” O’Riley wrote in a letter to BCUC chair David Morton. “As the evolution of the pandemic is uncertain and the date of resolution is unknown, various cost and scheduled impact scenarios continue to be assessed and refined as part of the re-baselining process.”

The incoming NDP government reluctantly decided to carry on with Site C, after former premier Christy Clark vowed to push the project “past the point of no return” before the 2017 B.C. election. In doing so, Premier John Horgan approved an updated cost estimate of $10.7 billion to complete it, an increase of about $1 billion from the initial estimate.

RELATED: Site C dam project carries on under NDP government

RELATED: NDP pays off $1.1B in B.C. Hydro debt, seeks rate cut

RELATED: After losing at every level, West Moberly sues again

Now the combined effects of COVID-19 and a series of problems have pushed the cost up by an amount not yet known. Those issues included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, and first nations treaty infringement claims and an injunction application.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote.

Before the COVID-19 pandemic, Site C was on track for completion by fall 2023 and full service to the B.C. Hydro grid by 2024.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureCoronavirusSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

EDITORIAL: Managing wildfires

Wildfires have the potential to cause significant damage within our province

Opening night lineup for online Roots & Blues festival released

The first night of the festival on Aug. 14 will be stacked with favourites from previous years

Revelstoke’s forestry museum launches podcasts and new website

One of their summer students is working remotely

Glimpses of Revelstoke’s past for Aug. 6

Chautauqua, CPR strike and destructive fire

Morning Start: The human body contains trace amounts of gold

Your morning start for Friday, August 7, 2020

53 new COVID-19 cases, no new deaths cap off week of high infection rates in B.C.

Roughly 1,500 people are self-isolating because they either have COVID-19 or have been exposed to it

VIDEO: Internet famous Yukon-based bhangra dancer explores Vancouver Island

Gurdeep Pandher spreads joy through dance, forms cross-cultural connections amid pandemic

Tech mogul growing North Okanagan’s wine industry

The founder of online dating site Plenty of Fish is developing 900 acres in Vernon

Fentanyl-laced powder being sold as cocaine in Kamloops

Interior Health has released a warning about very strong fentanyl in Kamloops

Unofficial holidays: the weird and wonderful things people celebrate around the world

On any given day of the year, there are several strange, silly or serious holidays to observe

North Okanagan ranch needs support to stay afloat

Founded in 1867, a fundraiser has been launched for the Historic O’Keefe Ranch

Video: Enraged man terrifies staff and customers at Shuswap restaurant

Video on Facebook shows the man hurling profanity at workers during the dinner rush on Aug. 7.

Moving on: Tanev scores 11 seconds into OT as Canucks oust Wild

Vancouver beats Minnesota 5-4 to move into first round of NHL playoffs

Number of Kelowna-linked COVID-19 cases grows to 159

Interior Health reported four new cases region-wide on Friday, 18 remain active

Most Read