A sixth turbine is being planned for the Revelstoke Dam.

BC Hydro proceeding with work on Revelstoke 6

Planning continues on sixth turbine for Revelstoke Dam, even following announcement by B.C. government approving construction of Site C dam

Planning continues on a sixth turbine for the Revelstoke Dam, even following last week’s announcement by the B.C. government of the construction of the Site C dam.

“In our base plan, Revelstoke 6 would be out in the 2029-2030 time frame,” said Randy Reimann, the director of resource planning for BC Hydro, in an interview with the Times Review last week. “If our expected case isn’t the way world unfolds, it could be needed as early as 2020. We’re working on having it available somewhere in that time frame.”

The Revelstoke Dam was completed in 1984 with space for six turbines but only four were installed at the time. A fifth turbine went into service in 2010.

Meanwhile, two more turbines are being installed at Mica Dam, with an expected in-service date of 2015.

That leaves Revelstoke 6 as the last turbine that can be readily installed in the  major Columbia River hydro dams.

The project was identified as being necessary in BC Hydro’s Integrated Resource Plan, which was accepted by the government in November 2013. Last week’s Site C decision doesn’t change that, said Reimann.

“What the plan actually said is with Site C and possibly some gas fired capacity on the north coast to support (liquid natural gas) and the load in the north coast region, we would have enough capacity to take us through to the late 2020s,” he said.

The plan is contingent on a number of factors, including LNG development and conservation measures. Reimann called it “an aspirational target.”

“There’s a number of reasons why our base resource plan may not be sufficient and to deal with those situations we identified two types of resources we wanted to move along and keep them ready for their earliest in-service date depending on how the future unfolds,” he said. “Those two resources are gas-fired generation or Revelstoke 6. Revelstoke 6 is really our main resource we want to look at for contingency purposes.”

The Revelstoke 6 project is currently in the environmental assessment phase. BC Hydro is working on an application for an environmental certificate — a project timeline says it hopes to have it place in 2017.

A core committee consisting of local government, First Nations and other stakeholders has been assembled to help guide the project, though it hasn’t met in several months.

“They’re looking at the project, helping us identity the effects of the project and recommending mitigation measures to address those affects and look at the operation of the sixth unit at Revelstoke Dam,” said Jen Walker-Larsen, a spokesperson for BC Hydro.

Jody Lownds, who is representing the North Columbia Environmental Society on the committee said the NCES’ goal is to make sure the cumulative impacts are being looked at. They were told only the incremental changes of adding a sixth turbine could be studied, “which makes it difficult to try and address some of the more extreme environmental impacts from the dam itself,” she said.

“One thing we keep hoping will be a possibility is for less daily fluctuation in the water level because that creates erosion issues,” Lownds added.

Walker-Larsen said the committee would likely be reconvened in the spring.

According to BC Hydro, Revelstoke 6 is expected to cost $420 million to install and would increase generation capacity by 500 megwatts. The Dam currently generates 2,480 MW when at full power.

“The additional capacity being built into the dam – we don’t have any more water – what it allows us to do is use the water at times we most need the electricity,” said Reimann. “It’s really being used to meet our peak demand.”

 

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Four staff members at the Okanagan Men’s Centre have tested positive for COVID-19 since Oct. 23, 2020. (Adult and Teen Challenge OMC photo)
Four positive COVID-19 cases at Okanagan Men’s Centre

Those affected are staff and have been in isolation since Oct. 23

Vince Schnabl looks at the view this October from the Gorge, west of Revelstoke. (Photo by Jon Wichett)
There’s 3 times more snow near Revelstoke than usual

According to 54 years of data from Parks Canada for Glacier National Park

Mail in ballot, provincial election 2020. (Liam Harrap/Revelstoke Review)
Mail-in-ballots coming in from Columbia River Revelstoke

In a progress report Elections BC said around 45 per cent of those issued have been returned

Mayor Gary Sulz (centre) cuts the ribbon for the new roundabout. Councillor Jackie Rhind (left) and Councillor Cody Younker (right) are on either side. (Liam Harrap/Revelstoke Review)
Revelstoke’s newest roundabout opens on Victoria Rd.

The project took approximately six months to complete

Revelstoke Drill Hall as it looked July 19, 1970; current home of Trans-Canada Fitness. (Estelle Dickey/Revelstoke Museum and Archives photo 392)
Glimpses of Revelstoke’s past for Oct. 29

Local history straight from the newspaper archives

A woman wears a face mask and plastic gloves while browsing books as a sticker on the floor indicates a one-way direction of travel between shelves of books at the Vancouver Public Library’s central branch, after it and four other branches reopened with limited services, in Vancouver, on Tuesday, July 14, 2020. (THE CANADIAN PRESS/Darryl Dyck)
B.C. reports 234 new COVID cases, 1 death of senior who had attended small birthday party

Roughly 5,700 people are isolating due to being exposed to a confirmed case

Superintendent of the Kelowna RCMP, Kara Triance. (Capital News file)
Non-violent crime, small population contributes to Kelowna’s crime rate spike, says RCMP

Kelowna RCMP is assuring the public the city is a safe place

RCMP. (Phil McLachlan - Black Press Media)
Crime up 31 per cent in Vernon in 2019: Statistics Canada

Increase includes a 45 per cent rise in violent Criminal Code violations

A Tuesday Oct. 27, 2020 apartment fire in Penticton killed two and displaced dozens more. (Brennan Phillips - Western News)
Fatal Penticton apartment fire deemed accidental

The blaze gutted an apartment building on Tuesday morning, killing two people and displacing dozens

A nurse performs a test on a patient at a drive-in COVID-19 clinic in Montreal, on Wednesday, October 21, 2020. THE CANADIAN PRESS/Paul Chiasson
Interior Health reports seven more COVID-19 cases

Eighty-nine cases remain active, none of whom are currently hospitalized

Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

Burnaby RCMP responded to a dine-and-dash suspect who fell through a ceiling in March 2020. (RCMP handout)
VIDEO: Suspected dine-and-dasher falls through ceiling of Burnaby restaurant

A woman believed to be dashing on her restaurant bill fell through the kitchen ceiling

This Photoshopped version of the crosswalks near the entrance to the Salmon Arm Arts Centre on Hudson Avenue show what is proposed to help create safety for and show inclusivity to the LGBTQ2S+ community. (Salmon Arm Arts Centre image)
Tri-rainbow crosswalk and Progress flag requested to help make Salmon Arm safe

Council will consider budget requests to help make city inclusive to LBGTQ2S+ community

A can of Canada Dry Ginger Ale is shown in Toronto on Thursday Oct. 29, 2020. The maker of Canada Dry Ginger Ale has agreed to pay over $200,000 to settle a class-action lawsuit launched by a B.C. man who alleged he was misled by marketing suggesting the soda had medicinal benefits. THE CANADIAN PRESS/Joseph O’Connal
B.C. man’s lawsuit over marketing of Canada Dry ginger ale settled for $200K

Soda’s maker, Canada Dry Mott’s Inc., denied the allegations and any liability

Most Read