Petronas LNG delay not due to B.C., Coleman says

Malaysian-led project still needs federal approval for site, CEO concerned about U.S. competition for gas exports to Asia

Lelu Island at the Prince Rupert port is the proposed location for an $11 billion LNG export terminal.

Malaysian oil and gas giant Petronas has put off its final investment decision on a large-scale liquefied natural gas project until some time in 2015, but it’s not because of B.C.’s taxes and conditions, says Natural Gas Development Minister Rich Coleman.

Pacific Northwest LNG, a consortium led by Petronas for a pipeline and terminal at the Prince Rupert port, issued a statement Wednesday citing construction costs and federal approvals it still needs for a pipeline and plants worth $36 billion.

“Costs associated with the pipeline and LNG facility remain challenging and must be reduced further before a positive final investment decision can be undertaken,” the statement says. “At the same time, Pacific Northwest LNG will continue to work to secure necessary regulatory and other approvals from the government of Canada.”

Coleman said he was consulted on the statement and remains optimistic about the project going ahead. The province set its tax and greenhouse gas rules for LNG projects during the fall legislature session, and completed agreements with the Nisga’a Nation to allow a gas pipeline to pass through their territory to the coast.

“It was always clear that once they got our piece completed, they would move on to making sure their numbers across the board with their partners work,” Coleman said. “That’s the pipeline, the upstream cost for gas plants, that’s the LNG plant itself, which they would build in Port Edward.”

Petronas CEO Shamsul Azhar Abbas said the decision will be made as soon as possible.

“This is vital in light of the current intense market environment and for Pacific Northwest LNG not to lose out on long-term contracts to competitive United States LNG projects,” Abbas said.

NDP natural gas critic Bruce Ralson called the decision “a setback,” noting that BG Group also cited U.S. competition in its recent decision to delay a final decision on its project for the Prince Rupert area.

 

Just Posted

Kelowna classroom where child allegedly overdosed re-opens after cleaning

An 8-year-old was unresponsive and unable to walk after ingesting an unknown substance at school.

Revelstoke’s Dam Survivors bring home bronze

The dragon boat team finished up their season with a medal

Glimpses of Revelstoke’s past for Sept. 12

120 Years Ago: Revelstoke Herald, Sept. 13, 1899 The memorial stone for… Continue reading

Revelstoke Community Calendar for Sept. 12

Bear Aware Affair Sept. 22, 4 p.m. Alley beside The Regent A… Continue reading

Growls and Hugs for Sept. 12

Someone or something got your hackles up? Or maybe someone made you… Continue reading

VIDEO: Vancouver Island mayor details emergency response after fatal bus crash

Sharie Minions says she is ‘appalled’ by condition of road where bus crashed

Federal party leaders address gun violence after weekend shooting near Toronto

One teen was killed and five people injured in the shooting

Video: Rain doesn’t deter Terry Fox runners in Salmon Arm

Dozens showed up to continue the Canadian icon’s marathon of hope.

Conservatives promise tax cut that they say will address Liberal increases

Scheer says the cut would apply to the lowest income bracket

B.C. VIEWS: Cutting wood waste produces some bleeding

Value-added industry slowly grows as big sawmills close

Fewer trees, higher costs blamed for devastating downturn in B.C. forestry

Some say the high cost of logs is the major cause of the industry’s decline in B.C.

Federal food safety watchdog says batch of baby formula recalled

The agency says it’s conducting a food safety investigation

Road block was costly legal battle for Summerland

Resolving Garnet Valley dispute took six years

Most Read