An artist’s rendering of the Site C dam, the third hydro dam on the Peace River. BC Hydro image

Site C dam project plagued by problems: expert

E. Harvey Elwin expresses concern about internal BC Hydro and government documents

The mammoth Site C hydro-electric project is seriously behind schedule, plagued by quality problems and marked by secrecy, says an assessment by an international dam expert.

E. Harvey Elwin – hired by a First Nation asking for a court injunction to aspects of the dam’s construction – expresses concern about work at the job site in his 196-page report citing internal BC Hydro and government documents, many of them previously confidential.

“In my opinion, it is the sign of a large performance problem with the (main) contractor meeting the requirements of the specifications and quality of work,” he wrote in the report filed Wednesday in B.C. Supreme Court.

In a letter accompanying a progress report to the B.C. Utilities Commission dated July 11, BC Hydro president Chris O’Riley said the project remains “on time and within budget.”

Spokespeople for the provincial government and contractor Peace River Hydro Partners did not immediately respond to requests for comment.

Elwin, who has worked on dams around the world including China’s Three Gorges project, concludes the dam’s construction is likely to take years longer than BC Hydro says.

READ MORE: Anti-Site C petition approved

The 1,100-megawatt dam and generating station on the Peace River in northern B.C. would flood parts of the traditional territory of the West Moberly and Prophet River First Nations.

In January they filed a civil court case, alleging their rights have been violated.

West Moberly also applied for an injunction to halt construction pending the outcome of the rights case. That motion goes to court Monday. Elwin’s report was filed in support of West Moberly’s case.

BC Hydro has argued any injunction would create heavy budget overruns. It says a two-year injunction would cost an extra $660 million and a three-year stoppage would cost $1.1 billion.

Based on documents BC Hydro was forced to release as part of the court process, Elwin disagrees.

He found that stopping work in 13 areas the West Moberly are most concerned about would delay completion of major milestones by a few months at most. He concluded the cost of a three-year injunction would be $71 million.

Elwin expresses serious concern at the number of reports detailing construction problems.

“I have observed that there are always a large number of (non-conformance reports) generated and being processed. It is also evident that many are not closed rapidly,” he writes. “The number, frequency, and lengths of time to close (such reports) are an indicator of the quality of work.”

Projections for placing concrete are “overly optimistic and not realistically achievable,” he says.

Last year, Elwin says contractors placed 35 per cent of the concrete they were supposed to for a major section of the dam. At that rate, Site C will take well over a decade to finish, significantly past its 2024 completion date, Elwin suggests.

O’Riley’s letter acknowledges the project has had problems meeting its construction schedule. It has also had safety concerns.

He said an agreement has been reached with the main contractor that will accelerate some activities and provide incentive payments to meet deadlines. That’s projected to cost up to $325 million.

“While the agreement will draw on our contingency budget … we have been able to manage the costs within the existing construction budget,” O’Riley wrote.

Elwin is skeptical.

“I seriously doubt the capability of the (main) contractor to take on and effectively perform to an accelerated schedule,” says his report.

The Canadian Press

Like us on Facebook and follow us on Twitter

Just Posted

Revelstoke Skating Club hosts Christmas performance

The Revelstoke Skating Club hosted their annual Christmas performance last Thursday evening.… Continue reading

Powder report: Rain in valley, snow on the ski hills

Get your ski gear ready as area mountains are ready for you to enjoy all the Interior winter has to offer this season.

Ballet Victoria comes to Revelstoke

Local dancers joined professionals in The Nutcracker

CP Holiday Train stops in Revelstoke

The CP Rail Holiday Train came through Revelstoke on Friday evening. Get… Continue reading

Busy day for Penticton Search and Rescue

PENSAR was called to three separate incidents Sunday, Dec. 16

Some types of cauliflower, lettuce recalled over E. coli fears

The Canadian Food Inspection Agency announced recall because of possible contamination.

CIBC shrinks event after Whistler mayor irks oil producers

After Whistler sent a letter to a Calgary-based oilsands giant, several energy firms said they would back out of the CIBC event.

Couple caught up in B.C. Legislature bomb plot to learn their fate

John Nuttall and Amanda Korody were arrested as part of an undercover RCMP sting on Canada Day 2013

Trial rights of accused spy for China at risk, lawyer tells Supreme Court

The lawyer for a man accused of trying to spy for China says federal foot-dragging over secrecy is endangering his client’s right to timely justice.

‘Recall fatigue’: Canadians may avoid certain foods over holidays

In the winter, Canada’s supply of fresh fruit and vegetables tends to come from very specific areas.

Shuswap business to provide fresh greens year round

Salmon Arm growers offer hydroponic test market to help develop signature salad mix

Interior Health offers new info tool for pregnant women

Moms-to-be with uncomplicated pregnancies can access tips by text or online

Shuswap farm market owner picks up oranges in California

Brad DeMille travels to U.S. to bring another 8,000 pounds of satsumas from family farm

Ryan Reynolds to narrate movie about B.C.’s Great Bear Rainforest

Vancouver-born actor known for Deadpool movies will voice film to be released Feb. 15, 2019

Most Read