B.C. pulls plug on power projects

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20

Wind turbine components await construction at independent power project near Chetwynd in 2008. High construction costs stalled B.C.'s first commercial wind energy project

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20 by the time a review of projects is complete, Energy Minister Bill Bennett said Thursday.

Bennett said the review is part of a broader effort by BC Hydro to meet his instruction to “spend less money,” as he leads an effort to reduce costs across all government operations.

BC Hydro proposed the move, identifying the 20 project proponents that were not meeting their contract obligations due to financing, regulatory or other problems. That non-performance gives BC Hydro legal authority to delay or terminate contracts.

The utility has contracts with 81 operating projects, mostly run-of-river hydroelectric, and another 47 are under construction or seeking permits after receiving purchase contracts.

BC Hydro released its latest draft resource plan last week, which estimates the province has enough electricity supply to meet growing demand for the next 10 years. Bennett said he is skeptical about that forecast, with population growth and industrial demand from new mines and natural gas development in northern B.C., but it gives the utility some breathing room.

“I’m a real fan of the clean energy industry, but obviously we don’t want to be agreeing to buy more power than what we need,” Bennett said.

BC Hydro has been criticized in recent years for running up billions in deferred debt, as it completes major expansion and seismic upgrading of its network of dams. A new power line to northeast B.C. has run over budget, and the NDP opposition has accused the government of forcing BC Hydro to buy private power at inflated rates through contracts running as long as 40 years.

Bennett said he has asked for a detailed analysis of the cost of private power compared to new sources such as the proposed Site C dam on the Peace River or adding turbines to BC Hydro dams on the Columbia River.

B.C.’s Clean Energy Act requires BC Hydro to be self-sufficient in electricity by 2016, based on an average rainfall year to replenish its hydro dams. The requirement is to minimize the import of power generated by burning coal or natural gas.

Just Posted

Yellow Vest movement rallied in Vernon Saturday

Protesters took to the steps of the Vernon courthouse Saturday.

Second CRED Talk looks at 50 years of change in Revelstoke Reach

While the Columbia River channel hasn’t changed, the ecology has greatly due to Hugh Keenleyside Dam

Avalanche control scheduled tomorrow on Highway 1 east of Revelstoke

Avalanche control work is scheduled along Highway 1 on Dec 15. From… Continue reading

Highlights from recent school board meeting in Revelstoke

Soon-to-arrive Syrian family, budget update, and upcoming silent action were discussed

Okanagan College unlocks time capsule

Items placed in 1993 and kept in capsule in library opened at special ceremony

Yellow Vest movement rallied in Vernon Saturday

Protesters took to the steps of the Vernon courthouse Saturday.

5 tips for self-care, mental wellness this holiday season

Ministry of Mental Health and Addictions urging British Columbians to prioritize self care through festive season

VIDEO: Craft growers will add to recreational market, cannabis producer says

Two B.C. men say their expertise in running small legal medical grow-ops a benefit to recreational market

Christmas wish for Mirielle: love and carpets

Mirielle was born with misshapen back legs and after a tough life on the streets, is looking for a forever home.

Vegan chocolatiers set up shop in Penticton

Celine Nativel and David Mullner, of Maison Mulnati French Vegan Chocolates, discuss their craft

World Sikh Organization demands Canada prove Sikh extremism is a threat

Sikh community says this is first time such extremism has been mentioned in federal terror-threat assessment

Risk of catching the flu increasing in B.C. this holiday season: BCCDC

Dr. Danuta Skowronski with the BC Centre for Disease Control says influenza will pick up during the holidays

Boeser has 2 points as Canucks ground Flyers 5-1

WATCH: Vancouver has little trouble with slumping Philly side

Shuswap tennis club’s indoor facility construction moving at a smooth clip

Volunteer support has been crucial, opening expected in April 2019.

Most Read