Site C dam project design has been changed to eliminate a separate bridge across the Peace River

Permits approved for Site C hydro dam

BC Hydro negotiating compensation with aboriginal communities, B.C. cabinet to decide soon whether $8 billion project will go ahead

VICTORIA – Both the federal and provincial governments have issued environmental assessment certificates for BC Hydro’s Site C dam, the proposed third hydroelectric project on the Peace River in northeastern B.C.

The approvals include dozens of legally binding conditions, including a $20 million farmland enhancement fund to offset river bottom land that would be flooded, and compensation for local aboriginal groups whose historic treaty rights to hunting, fishing and trapping would be affected.

Cost of the project, last estimated by BC Hydro at $7.9 billion, will factor into a final decision by the B.C. cabinet whether to go ahead with the dam. Energy Minister Bill Bennett has indicated he expects the final investment decision to be made by the end of 2014, and if it’s approved, work would begin immediately.

Among the 77 B.C. conditions is an aboriginal business participation strategy to share the estimated 10,000 person-years of construction work the dam project would generate.

Seven aboriginal communities affected by the proposal have been offered cash and Crown land to compensate for land lost by construction of the dam. All are signatories to Treaty 8, which ensures their rights to hunt, trap and fish as they did before the treaty was signed in 1899. Officials say five of the seven are currently in negotiations.

Situated near Fort St. John and downstream of the W.A.C. Bennett and Peace Canyon dams, Site C’s 1,050-metre-long earthfill dam would create a reservoir 83 km long and two to three times the current width of the river.

It requires two power lines built in the same corridor as the existing line, and six water turbine generators that would produce enough electricity to power about 450,000 homes.

BC Hydro estimates that because Site C would use water held back in the existing Williston Lake reservoir, it would generate 35 per cent of the energy as the Bennett dam with only five per cent of the reservoir area.

 

Just Posted

‘Art Alleries’ coming to Revelstoke with funding from the Columbia Basin Trust

Rob Buchanan’s creations will be hung on alleyway walls and lit

Animal rights activists to protest Kelowna’s RibFest launch

Animal rights activists plan on sinking their teeth into an annual event they say is unethical and unhealthy.

No end in sight, smoke is here to stay

There is no anticipated change in weather for the Okanagan-Shuswap this week

B.C. declares state of emergency as more than 560 wildfires rage

This is only the fourth state of emergency ever issued during a fire season

LUNA Q&A: Isabelle Kirouac

Meet the artists of LUNA Noctural Art & Wonder coming to Revelstoke Sept. 29

Interim GoFundMe payments approved in Humboldt Broncos crash

$50,000 to be given to each of the 13 survivors and each family of the 16 people who died

Ottawa intervenes to get B.C. ball player, 13, to Little League World Series

Before immigration issue was resolved, Dio Gama was out practicing the game he loves Wednesday

Pet goldfish invades small B.C. lake

Pinecrest Lake is located between Whistler and Squamish

Mounties deployed to help B.C. communities affected by wildfires

RCMP officers heading to places particularly within central, northern and southern B.C.

Chinese medicine practitioner in B.C. facing historical sex assault charges

71-year old Kit Wong practiced acupuncture from his home during the time of the assaults

Quebec sets aside $900 million for companies hurt by U.S. tariffs

Premier Philippe Couillard says his government will make $863 million available over five years

Wildfires converge near Mabel Lake in Lumby

Area restrictions expanded in Lumby and Cherryville

Super League Triathlon makes North American debut in Penticton

Making its North American debut, the event brings a new twist to the traditional sport

Most Read