Ian Anderson, President and CEO of Trans Mountain, speaks during an event to mark the start of right-of-way construction for the Trans Mountain Expansion Project, in Acheson, Alta., Tuesday, Dec. 3, 2019. THE CANADIAN PRESS/Jason Franson

Trans Mountain pipeline will be the ‘best darn pipeline in the world,’ says CEO

Pipeline expansion is expected to take 30 to 36 months to build

The CEO of Trans Mountain says he’s “a little greyer” than he was 10 years ago when planning began for an expansion of the Edmonton-to-Burnaby oil pipeline but he’s still proud to oversee the official launch of Alberta construction.

Ian Anderson, who switched employers when the pipeline and its proposed expansion were sold to the federal government in 2018 for $4.5 billion, repeated a vow Tuesday to have expansion project pipe in the ground before Christmas.

Speaking in a frosty field west of Edmonton, he said the project has been steadily improved as it was repeatedly delayed over the years and is now set to be the “best darn pipeline in the world” with enhanced leak detection and thicker pipe in key segments.

He said the pipeline will take 30 to 36 months to build, which means it could be completed in the second half of 2022, but he declined to update the last cost estimate of $7.4 billion because the schedule is not yet confirmed.

Federal Minister of Natural Resources Seamus O’Regan said the event and the opening of the Canadian part of Enbridge Inc.’s Line 3 export pipeline last weekend make it a “good week” for Canada.

Alberta Energy Minister Sonya Savage said it’s “crucial” the Trans Mountain project not be subject to any further delays after it had to be approved twice by the federal government because of court challenges.

The expansion will nearly triple the 300,000-barrel-a-day capacity of the existing Trans Mountain pipeline, which carries crude oil and refined products from Edmonton to a terminal in Burnaby, B.C.

READ MORE: Trans Mountain received $320M in government subsidies in first half 2019: report

READ MORE: B.C. First Nations drop out of court challenge, sign deals with Trans Mountain

READ MORE: Feds won’t explain claim pipeline expansion will raise $500M in tax revenue

The Canadian Press


Like us on Facebook and follow us on Twitter.

Just Posted

Revelstoke schools graffitied

Revelstoke Secondary School and Begbie View Elementary were defaced last weekend

Parks Canada on the way to completing $122 million in infrastructure projects

Upgrades in Mt. Revelstoke and Glacier National Park have been in progress for five years

Highway 1 closed east of Golden

Due to rocks on highway

Snowfalls cost $3,500 per cm to plow in Revelstoke

This year’s snow removal budget is $1.3 million

‘A loud sonic boom’: Gabriola Island residents recount fatal plane crash

Area where the plane went down is primarily a residential neighbourhood, RCMP say

Thunberg ‘a bit surprised’ to be Time ‘Person of the Year’

‘I could never have imagined anything like that happening,’ she said in a phone interview

B.C. patients wait 41% longer than national average to see a walk-in doctor: Medimap

The longest wait time was found in Sidney, B.C., where patients waited an average of 180 minutes

Toronto Raptors, Don Cherry top the list of Canadians’ Google searches in 2019

‘Champions’ was the theme of the last year, Google said

Morning start: Did you know there is a Scottish tartan designed for Mars exploration?

Your morning start: Fun fact, weather, and video of the day

Tavares scores twice as Maple Leafs earn 4-1 win over Canucks

Vancouver sees two-game win streak snapped

UPDATED: No survivors in Gabriola Island plane crash: RCMP

Coroner confirms multiple fatalities after small plane goes down Tuesday night near Nanaimo

VIDEO: Harbour Air makes history with first electric aircraft test flight

Successful flight marks first of its kind in the world

The Grinch who Stole a Hedge: Security camera captures Chilliwack tree theft

RCMP arrives as person calmly walks away with tree in downtown area

Most Read